Bright key facts / Deployed

A hybrid cooling system cut direct water use at an operating national-laboratory data center.

DOE reports that NREL’s thermosyphon hybrid system avoided 2.10 million gallons over two years and cut data-center water use in half by using dry heat rejection when weather allowed while retaining a cooling tower for peak conditions.

AI’s role
The HPC facility supports advanced computing; the documented result is conventional thermal engineering and measured operating water reduction, not an AI-model outcome.
Documented result
A May 2019 DOE case study reports that the roof-mounted thermosyphon cooler avoided 1.16 million gallons in its first operating year and 2.10 million gallons over two years, cutting data-center water use in half. Controls route heat to campus reuse first, dry rejection when conditions permit, and the existing open cooling tower for remaining and peak loads.
Important limitation
The result comes from a 10,000-square-foot national-laboratory HPC facility, not a hyperscale commercial campus.

Source published 2019-05-01 · Bright published 2026-09-19 · Evidence and limitations