A Finnish district-heating network has used data-center heat since 2015.

Original sources ↓ · Revision history ↓

Deployed · source published 2025-08-27

MÄNTSÄLÄ, FINLAND / HEAT

Since 2015, the local utility Nivos has moved recovered server heat into Mäntsälä’s town-centre district-heating network. Heat exchangers collect warmth from exhaust air; electric heat pumps raise its temperature so connected homes and other properties can use it.

≈ 1/3of town-centre district heat, reported by Nivos in 2025
How the documented system connects
01SERVER AIR02EXCHANGER03HEAT PUMP04TOWN NETWORK

Waste heat becomes useful only after a temperature lift

Server rooms produce a steady stream of low-temperature heat. In Mäntsälä, heat exchangers capture warmth from the data center’s exhaust air and electric heat pumps lift it to the temperature required by the district network. Nivos then distributes it to properties connected in the town centre.

The network and a nearby customer base matter as much as the servers. Nivos keeps other heat sources available for reliability, and a 2025 municipal assessment says expanding the existing network northward is difficult without larger heat customers.

Why the annual figures differ

The sources describe different periods and measures. A Nivos reference updated in 2019 described 30 gigawatt-hours a year after a 2018 enhancement. Equipment supplier Calefa’s undated reference cites 25 gigawatt-hours a year. Nebius estimated roughly 20,000 megawatt-hours annually in October 2024. The most recent utility statement Bright found, from August 2025, says recovered heat supplied about one-third of the town-centre network.

Bright therefore does not present one timeless annual-output number. The operating fact is clear; current metered delivery, heat-pump electricity, price, and displaced emissions still need consistent annual disclosure.

A place-specific public benefit

Connected homes and other properties receive district heat, but the public sources do not identify individual customers. The result depends on a utility willing to buy and move the heat, sufficient nearby demand, electric heat pumps, pipes, commercial terms, and backup supply.

The original operator was Yandex. Nivos now identifies the operating company as Global DC Oy, wholly owned by Nebius Group.

Source history & evidence assessment
Maturity
Deployed
Claim confidence
medium
Event date
2015
Source published
2025-08-27
Captured
2026-09-19
Last source review
2026-09-19
Editorial method
AI-assisted source review
Place / relevance
Mäntsälä, Finland · operating-facility

Bright compared this account with the linked original and supporting sources and kept reported, budgeted, projected, and observed claims distinct. Bright did not independently audit the underlying records.

Maturity describes the tested or operational setting. Confidence describes support for the particular claim; one does not determine the other.

Original sources

Nivos update on the Mäntsälä data center and heat recovery · institution

Nivos operational update on data-center heat · institution

Nivos historical reference on the Mäntsälä heat-recovery plant · institution

Calefa supplier reference for the Mäntsälä heat-pump plant · institution

Nebius October 2024 Mäntsälä expansion and heat-recovery release · institution

Institutions: Nivos · Nordic Investment Bank · Municipality of Mäntsälä

Explore the underlying question

Revision & correction history

2026-09-19 · Added direct historical Nivos, Calefa and Nebius citations; separated their dated 20, 25 and 30 gigawatt-hour claims; retained Nivos’s 2025 one-third network share as the clearest recent denominator.

No corrections recorded.